Question everyone. We're starting on a cabin next spring on my hunting property in East central Minnesota. It will be a 30x60 pole shed, half living space, half garage. Full slab underneath everything.
Obviously, this is in a rural area. I won't have a septic system installed for some time due to cost, but of course I want to install all the sewer/drain pipe below the slab during construction. I'll plumb under the slab for a kitchen sink and a bathroom with sink, shower, and toilet.
My question is this. I'm planning on running a 4 inch pipe out beyond the edge of the slab and capping it off. I'm assuming that any pipe that goes out of the slab has to be below the frost line or it will risk freezing and this applies to waste pipe. Correct?
Assuming above is correct, how far below grade does this pipe need to be at the point that it exits the slab? Does it need to be all the way below the frost line at this point?
Or do you just let the natural 1/4 inch per foot drop play out and it ends up wherever it ends up, and then put on like a 45 bend at the slab edge to start dropping quickly to get below the frostline?
Any other advice, "be sure you do", or other suggestions appreciated.
Thanks.
Grouse
Obviously, this is in a rural area. I won't have a septic system installed for some time due to cost, but of course I want to install all the sewer/drain pipe below the slab during construction. I'll plumb under the slab for a kitchen sink and a bathroom with sink, shower, and toilet.
My question is this. I'm planning on running a 4 inch pipe out beyond the edge of the slab and capping it off. I'm assuming that any pipe that goes out of the slab has to be below the frost line or it will risk freezing and this applies to waste pipe. Correct?
Assuming above is correct, how far below grade does this pipe need to be at the point that it exits the slab? Does it need to be all the way below the frost line at this point?
Or do you just let the natural 1/4 inch per foot drop play out and it ends up wherever it ends up, and then put on like a 45 bend at the slab edge to start dropping quickly to get below the frostline?
Any other advice, "be sure you do", or other suggestions appreciated.
Thanks.