Another one for you construction and framing wizards.
The Kitchen Build saga (Rabbit Hole!) continues!
If you've been following along, removing three walls to make three rooms (which were all built as additions or extensions in different decades) into one large room has brought some challenges.
The Ceilings were all in different planes and not level. So I sistered material to the joists to bring them all down level with the lowest point in the space, and installed strapping perpendicular to prep for drywall. This was an interesting challenge, but glad I took it on. My drywall guy approves!
I've discovered though that the floors suffer from the same problem. (in hindsight I should have seen this coming!)
Bear with me as I explain!
Reference image (this pic was taken before the ceiling was finished, but that doesn't matter for this thread)
The thick purple line represents the location of the original outside foundation wall of the house as built in the 60's before anything was added on. There's a cinder block foundation wall below the purple line and the blue lines are the direction the joists run.
Then in 1991 the kitchen was bumped out into the area with the green lines. The thick green line on the right has a cinder block foundation wall below it (and used to be an exterior wall) and these joists run left to right as drawn in green. Below this space is a ~4' crawl-space with concrete floor. This area has a a cathedral ceiling/roof whereas the main house has a shed roof in the opposite direction which is presumably why they put the joists in that direction)
Then in 2010 the space between the kitchen bump out (green) and what was a porch off to the right (outside the photo) was filled in with what I have outlined in orange (filled in while at the same time turning the porch into real living space.) The thick orange line on the right also has a cinder block foundation wall below it and is "unexcavated crawlspace" below (i.e. dirt about 4' down)
So....
Unfortunately it seems over the 31 years since this bump out ("green") was added, it's settled at the sliding door end, such that as you walk from point "A" to "B" you are walking down-hill. It's not dramatic, but enough to feel it, and it's a full (almost exactly) 3/4" offset/slope from where the addition joined the existing house to where the sliding doors are. The whole sliding door end settled evenly, it's all level at that end left to right, just not front to back.
The whole upper area (original house where the blue joists are drawn) is nice and flat, solid and level. The corner I've now exposed (outlined in orange) by removing the two walls is also level, but sits ~3/8" below the subfloor in the original area outlined in blue. This corner also sags in the middle and is very bouncy (the center 2x8 joist appears to be cracked at a large knot.
So, "blue" is all good. "Orange" is level (but could use some stiffening) and is a bit too low. "Green" aligns well at point "A" but then slopes away, so at the sliders, the sub-floor in the orange area is basically flush with the finished floor in the green. (that missing chunk of hardwoods in the blue area were never installed, there used to be a base cabinet there.)
So I think the solution is effectively the same thing I did on the ceiling. Poke holes in my plan please, or offer new suggestions!
1. Use a circular saw and guide to cut through the hardwood floor straight across along the thick purple line.
2. Carefully pry up and remove all the hardwoods in the "Green" area, clipping the staples so I can reuse most of the boards. Leave hardwoods in place in the Blue area.
3. Cut out all sub-floor plywood in the Green and Orange areas exposing all joists.
4. Use a 360* laser level and sister new 2x6 joists to all existing joists using glue and construction screws, bringing them all into the same plane level with the "blue" field at the thick purple line (level, but offset the thickness of the hardwoods and sub-floor so once built up it'll be in the same plane)
5. Apply a new skin of 3/4 or 5/8 plywood sub floor using glue and screws.
6. Install hardwoods, feathering into the blue area which was otherwise left untouched.
I had considered replacing steps 3-5 with "use a self leveling compound" but I'm not sure I can go to a full 3/4" thickness with such a material and taper it to nothing. seems messy and possibly inconsistent.
I am also partly concerned that once the floor at the sliders is 3/4" higher than it is now, the sliders might want to be removed and re-installed an inch or so higher. I'll deal with deciding that later I suppose.
thoughts??
The Kitchen Build saga (Rabbit Hole!) continues!
If you've been following along, removing three walls to make three rooms (which were all built as additions or extensions in different decades) into one large room has brought some challenges.
The Ceilings were all in different planes and not level. So I sistered material to the joists to bring them all down level with the lowest point in the space, and installed strapping perpendicular to prep for drywall. This was an interesting challenge, but glad I took it on. My drywall guy approves!
I've discovered though that the floors suffer from the same problem. (in hindsight I should have seen this coming!)
Bear with me as I explain!
Reference image (this pic was taken before the ceiling was finished, but that doesn't matter for this thread)
The thick purple line represents the location of the original outside foundation wall of the house as built in the 60's before anything was added on. There's a cinder block foundation wall below the purple line and the blue lines are the direction the joists run.
Then in 1991 the kitchen was bumped out into the area with the green lines. The thick green line on the right has a cinder block foundation wall below it (and used to be an exterior wall) and these joists run left to right as drawn in green. Below this space is a ~4' crawl-space with concrete floor. This area has a a cathedral ceiling/roof whereas the main house has a shed roof in the opposite direction which is presumably why they put the joists in that direction)
Then in 2010 the space between the kitchen bump out (green) and what was a porch off to the right (outside the photo) was filled in with what I have outlined in orange (filled in while at the same time turning the porch into real living space.) The thick orange line on the right also has a cinder block foundation wall below it and is "unexcavated crawlspace" below (i.e. dirt about 4' down)
So....
Unfortunately it seems over the 31 years since this bump out ("green") was added, it's settled at the sliding door end, such that as you walk from point "A" to "B" you are walking down-hill. It's not dramatic, but enough to feel it, and it's a full (almost exactly) 3/4" offset/slope from where the addition joined the existing house to where the sliding doors are. The whole sliding door end settled evenly, it's all level at that end left to right, just not front to back.
The whole upper area (original house where the blue joists are drawn) is nice and flat, solid and level. The corner I've now exposed (outlined in orange) by removing the two walls is also level, but sits ~3/8" below the subfloor in the original area outlined in blue. This corner also sags in the middle and is very bouncy (the center 2x8 joist appears to be cracked at a large knot.
So, "blue" is all good. "Orange" is level (but could use some stiffening) and is a bit too low. "Green" aligns well at point "A" but then slopes away, so at the sliders, the sub-floor in the orange area is basically flush with the finished floor in the green. (that missing chunk of hardwoods in the blue area were never installed, there used to be a base cabinet there.)
So I think the solution is effectively the same thing I did on the ceiling. Poke holes in my plan please, or offer new suggestions!
1. Use a circular saw and guide to cut through the hardwood floor straight across along the thick purple line.
2. Carefully pry up and remove all the hardwoods in the "Green" area, clipping the staples so I can reuse most of the boards. Leave hardwoods in place in the Blue area.
3. Cut out all sub-floor plywood in the Green and Orange areas exposing all joists.
4. Use a 360* laser level and sister new 2x6 joists to all existing joists using glue and construction screws, bringing them all into the same plane level with the "blue" field at the thick purple line (level, but offset the thickness of the hardwoods and sub-floor so once built up it'll be in the same plane)
5. Apply a new skin of 3/4 or 5/8 plywood sub floor using glue and screws.
6. Install hardwoods, feathering into the blue area which was otherwise left untouched.
I had considered replacing steps 3-5 with "use a self leveling compound" but I'm not sure I can go to a full 3/4" thickness with such a material and taper it to nothing. seems messy and possibly inconsistent.
I am also partly concerned that once the floor at the sliders is 3/4" higher than it is now, the sliders might want to be removed and re-installed an inch or so higher. I'll deal with deciding that later I suppose.
thoughts??